BELGARD® WALL INSTALLATION
 
Installation - Retaining Walls
1. Excavation Dig a trench that will be deep enough to contain the foundation materials, as well as the first row (or first several rows) of blocks. As a general rule, 10% of the wall's height should be buried in the ground.
2. Preparation of the base Install a geotextile membrane to prevent the soil from obstructing the drainage system.
3. Foundation Prepare the foundation with crushed stone. Compact this layer. Place a perforated drain on top of the compacted stone. The drain will be covered with clean stone in step 5.
4. First Row Place the first row of blocks on the compacted foundation. Make sure they are level.
5. Building the wall Install the following rows of blocks. Fill the space behind the blocks with clean stone.
6. Finishing Install the last row of blocks or the caping modules, depending on the type of product you have chosen. Cover the clean stone with the geotextile membrane. Fill and level the soil behind the last row of blocks to complete the job. Note: It is important to glue the capping modules with a concrete adhesive.
Scott Stone - Installation - Retaining Walls
Continue
Belgard®
For More Information call: 800-649-8782
 
top
For more information about this product, Contact Us or Call 1 800-649-8782
About Us | Products | Services | Photo Gallery | Projects Gallery